Traffic Control Lookahead


Subscribe for Updates
Join our email list and stay informed about construction.



- Nov 17
Thanksgiving Holiday Hours


- Nov 3
New Traffic Shift and Increased Construction Activity Underway


- Oct 20
Second Major Construction Weekend Starts Friday, Traffic Shift to Follow


- Oct 13
The first of two major construction weekends begins this Friday, October 13 at 9 p.m.


- Oct 6
Paving Next Week, Marathon Weekends to Follow


- Sep 29
October Schedule Lookahead


- Sep 15
Lane Shifts and Access Changes Now to December 2024 Los Altos Parkway to Golden View Drive

- Aug 31
Anticipate Closures After Labor Day Weekend


- Aug 24
Removal of "Pork Chop" Islands at Los Altos Intersection Thursday Night


- Aug 18
Crews Install Storm Drain Across Kohl's Access Road

- Aug 11
Earthwork at Los Altos Parkway Closes Kohl's Secondary Access through October


- Aug 4
Major Operations Resume Sunday Night: Expect Nightly SB and NB Lane Closures


- Jul 28
Major Operations on Pause for Hot August Nights


- Jul 21
Drainage Crossing Complete, Major Roadway Repairs on I-80


- Jul 14
Southbound Pyramid Closure Extended

- Jun 30
4th of July Holiday


- Jun 24
24-hour Operations Begin Sunday Through December 2023


- Jun 9
Earthwork Continues; Night Work Next Two Weeks


- Jun 2
Northern Nevada Business Weekly Reports on the Project