Construction Schedule

Phase 1 construction began May 2023 and is expected to be complete in the summer of 2025.

The schedule is weather permitting and subject to change.

The construction schedule is split into three parts:

01

COMPLETE

​Southbound (SB) Queen Way to Los Altos   May - Nov. 2023

Roadway and slope excavation, roadway fills, drainage work, nighttime pipe work, installation of retaining wall, aggregate base and initial paving for new widening, resurfacing of the existing roadway, riprap (large rock) and other erosion control measures

02

COMPLETE

Northbound (NB) Queen Way to Los Altos   Nov. 2023 - Oct. 2024

Roadway and slope excavation, roadway fills, drainage work, nighttime pipe work, aggregate base, curb and gutter, sidewalk, new concrete barrier rail, intelligent transportation systems (ITS) and other electrical infrastructure

03

All of Los Altos to Golden View Drive   Sept. 2023 - Dec. 2024

Roadway and slope excavation, roadway fills, drainage work, nighttime pipe work, installation of multiple sound/screen walls, aggregate base, curb and gutter, sidewalk, new concrete barrier rail, intelligent transportation systems (ITS) and other electrical infrastructure, initial paving and resurfacing of roadway, riprap and other erosion control measures

Working Hours

Normal hours are Monday - Friday, 6 a.m. to 5 p.m.

 

Nighttime hours:

SB work is Sunday - Friday, 8 p.m. to 5 a.m.

NB work is Sunday - Friday, 9 p.m. to 7 a.m.