Major Operations on Pause for Hot August Nights
Photo courtesy of Travel Nevada Work will conclude Friday, July 28 at 5 p.m. and resume Sunday, August 6 at 8 p.m. Some utility work will...
Jul 28, 2023
10 views


Drainage Crossing Complete, Major Roadway Repairs on I-80
Southern Drainage Crossing Complete Crews completed the southern underground storm drain crossing this week and there will be no nightly...
Jul 21, 2023
11 views


Southbound Pyramid Closure Extended
Due to ongoing pipe crossing work, the nightly southbound closure on Pyramid Highway has been extended through Friday, July 21. Commuters...
Jul 14, 2023
6 views


4th of July Holiday
In observance of Independence Day, construction operations will conclude Friday, June 30 by 6 p.m. Work resumes Thursday, July 5 at 8...
Jun 30, 2023
13 views


24-hour Operations Begin Sunday Through December 2023
Work will be occurring 24-hours-a-day starting Sunday, June 25 at 8 p.m. through December. Crews will be installing new underground...
Jun 24, 2023
9 views