Construction Schedule

Phase 1 construction began May 2023 and was completed on time in July 2025.

01

COMPLETE

​Southbound (SB) Queen Way to Los Altos   May - Nov. 2023

Roadway and slope excavation, roadway fills, drainage work, nighttime pipe work, installation of retaining wall, aggregate base and initial paving for new widening, resurfacing of the existing roadway, riprap (large rock) and other erosion control measures

02

COMPLETE

Northbound (NB) Queen Way to Los Altos   Nov. 2023 - Oct. 2024

Roadway and slope excavation, roadway fills, drainage work, nighttime pipe work, aggregate base, curb and gutter, sidewalk, new concrete barrier rail, intelligent transportation systems (ITS) and other electrical infrastructure

03

COMPLETE

All of Los Altos to Golden View Drive   Sept. 2023 - Summer 2025

Roadway and slope excavation, roadway fills, drainage work, nighttime pipe work, installation of multiple sound/screen walls, aggregate base, curb and gutter, sidewalk, new concrete barrier rail, intelligent transportation systems (ITS) and other electrical infrastructure, initial paving and resurfacing of roadway, riprap and other erosion control measures

Building Phase 1

181,000 cubic yards of earth removed to make way for wider highway lanes

37,000 tons of new pavement base placed

Installed nearly 15,000 linear feet of multi-use path and sidewalk

More than 300,000 hours spent in construction