Paving Next Week, Marathon Weekends to Follow

October 9-13: Paving Widened West Side

Next week, crews will pave the new widened section of highway on the west side between Queen Way and Los Altos Parkway.

Paving will occur during the daytime and drivers can expect to see an increase in truck traffic in the area. Construction vehicles and trucks enter the work zone via southbound Pyramid near Los Altos Parkway, and they exit the work zone at the Farr Lane intersection.

Drive with caution and obey the speed limit while going through the work zone.

 

October 13-16 & 20-23: Major Construction Weekends

Two major construction weekends, also known as "marathons", are planned for the following weekends:

  • Weekend 1: Friday, October 13 at 9 p.m. to Monday, October 16 at 5 a.m.

  • Weekend 2: Friday, October 20 at 9 p.m. to Monday, October 23 at 5 a.m.

These marathon weekends will allow crews to install necessary underground drainage across the highway as quickly as possible and help expedite the overall construction schedule.

During the nighttime hours, between 11 p.m. and 5 a.m., the Los Altos Parkway/Pyramid intersection will be FLASHING RED. Drivers should treat the flashing red intersection like a four-way stop.


Speed through the work zone will be reduced to 35 MPH. Click on the maps below to see other traffic and access changes.



Construction operations are weather dependent and subject to change.